Project                         Station Square Condominium
Owner                         Station Square Clearwater Condo, LLC.
Architect                      Kip E. Daniel Architect
Engineer                      KTD Consulting Engineers
General Contractor     Biltmore Construction Company, Inc.
Start Date                    February, 2007                       
Contract Amount         $2,045,838

Project                         Brandon Regional Service Center
Owner                         Hillsborough County, Florida
Architect                      Woodroffe Corporation Architects
Engineer                      A. J. Sanchez
General Contractor     Bandes Construction
Start Date                    January, 2007            
Contract Amount         $562,000

Project                         Durant High School Classroom Addition
Owner                         School District of Hillsborough County
Architect                      Reynolds Smith & Hill Architect
Engineer                      Anston-Greenlees, Inc.
General Contractor     Christiano Construction Company
Start Date                    December 2006                     
Contract Amount         $487,000

Project                         Tampa Bay Water Emergency Management Building
Owner                         Tampa Bay Water
Architect                      Collman Karsky Architects
Engineer                      SI Engineering
General Contractor     Biltmore Construction Company, Inc.
Start Date                    March, 2007               
Contract Amount         $450,000

Project                         Brandon  High School Classroom Addition
Owner                         School District of Hillsborough County
Architect                      Reynolds Smith & Hill Architect
Engineer                      Anston-Greenlees, Inc.
General Contractor     Christiano Construction Company
Start Date                    December 2006                     
Contract Amount         $431,000

Project                         Kingswood Elementary School Renovation
Owner                         School District of Hillsborough County
Architect                      Carruthers
Engineer                      CEA, Inc.
General Contractor     Manhattan Construction
Start Date                    March, 2007               
Contract Amount         $423,000 

Project                         Ultimate Medical Academy
Owner                         Ultimate Medical Academy
Architect                      Baker Barrios Architects
Engineer                      Mechanical Engineering Solutions, Inc.
General Contractor     Cork Howard Construction
Start Date                    February, 2007                       
Contract Amount         $231,770

Project                         Grand Central at Kennedy White Box Offices
Owner                         Grand Central
Architect                      Scott Architects, Inc.
Engineer                      Milan Engineering
General Contractor     Integra Construction Group
Start Date                    April, 2007                  
Contract Amount         $129,000

Project                         Brandon Regional Hospital CT Renovation
Owner                         HCA, Inc.
Architect                      Harvard Jolly Architect
Engineer                      Smith Sekman & Reed
General Contractor     Hinson Building Corporation
Start Date                    January, 2007
Contract Amount         $76,450

Project                         Bayonet Point Medical Center
Owner                         HCA, Inc.
Architect                      Harvard Jolly Architect
Engineer                      Smith Sekman & Reed
General Contractor     Hinson Building Corporation
Start Date                    January, 2007
Contract Amount         $52,500.00

 